Eutectoid steel is fully austenitized at 1073 K, rapidly cooled to the specified hold, and finally quenched to 300 K. Match P300 K indefinitely, Q873 K for4 min, R673 K for20 min, S623 K for2 min with 1 bainite,2 martensite,3 pearlite,4 bainite + martensite. Use the TTT diagram.

Diagram for GATE 2025 XE — all source sections question 56
  1. P – 3; Q – 2; R – 1; S – 4
  2. P – 2; Q – 3; R – 1; S – 4
  3. P – 2; Q – 1; R – 3; S – 4
  4. P – 4; Q – 3; R – 1; S – 2

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) P – 2; Q – 3; R – 1; S – 4

Explanation

A rapid quench to 300 K passes below martensite finish, P–2. Holding873 K for240 s completes pearlite, Q–3. At673 K,1200 s completes bainite, R–1. At623 K,120 s gives partial bainite; remaining austenite becomes martensite on quenching, S–4. Thus B, using the plotted start/finish curves.