GATE 2025 CS (CS2) – Question 61
An application executes $6.4 \times 10^8$ number of instructions in 6.3 seconds. There are four types of instructions, the details of which are given in the table. The duration of a clock cycle in nanoseconds is _________. (rounded off to one decimal place)
| Instruction type | Clock cycles required per instruction (CPI) | Number of instructions executed |
|---|---|---|
| Branch | 2 | $2.25 \times 10^8$ |
| Load | 5 | $1.20 \times 10^8$ |
| Store | 4 | $1.65 \times 10^8$ |
| Arithmetic | 3 | $1.30 \times 10^8$ |
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 3
Explanation
Total cycles for the program $=\sum(\text{CPI}\times\text{count})$:
$$2(2.25)+5(1.20)+4(1.65)+3(1.30)=4.5+6.0+6.6+3.9=21.0\ (\times10^8\text{ cycles}).$$
So the program takes $2.1\times10^9$ cycles. Execution time is $6.3$ s, hence
$$\text{cycle time}=\frac{6.3\text{ s}}{2.1\times10^9}=3.0\times10^{-9}\text{ s}=\mathbf{3.0}\text{ ns}.$$