GATE 2024 CH – Question 8

General Aptitude · Quantitative Aptitude: Data Interpretation, Arithmetic and Number Computation · 2 marks · Multiple choice

The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).

The Capacity Factor of a power generation technology is: Capacity Factor = $\frac{\text{Electricity Generation (MWh)}}{\text{Installed Capacity (MW)} \times 1000\text{ (h)}}$

Which one of the given technologies has the highest Capacity Factor?

Diagram for GATE 2024 CH question 8
  1. T1
  2. T2
  3. T3
  4. T4

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (A) T1

Explanation

The capacity factors are: T1 $\frac{10000}{20 \times 1000} = 0.50$, T2 $\frac{9000}{30 \times 1000} = 0.30$, T3 $\frac{7000}{15 \times 1000} = 0.47$, T4 $\frac{12000}{40 \times 1000} = 0.30$. The highest is T1.