GATE 2023 CE (CE2) – Question 20

Irrigation · Canals, design of weirs on permeable foundation, cross drainage structures · 1 mark · Multiple choice

Identify the cross-drainage work in the figure.

natural drainage stream is carried in a trough above a canal; the canal full supply level is below the trough bottom.
  1. Super passage
  2. Aqueduct
  3. Siphon aqueduct
  4. Level crossing

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (A) Super passage

Explanation

Identify the work from how the two waterways cross, as described in the figure: the natural drain is carried in a trough **above the canal**, and the canal flows freely below it (the canal full supply level is below the trough bottom).

Answer **Super passage** (A).