GATE 2022 CE (CE2) – Question 53
Activities: A (10 days, none); B (12, none); C (5, after A); D (14, after B); E (10, after B and C). Find total float of E (integer days).
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 1
Explanation
Forward pass: A finishes at 10, B at 12, C at 15, D at 26. E starts at max(12,15)=15 and finishes at 25. The project completes at 26.
E can finish at day 26 without delaying the project, so its total float is 26−25=**1 day**.