GATE Construction Management: Project planning and scheduling: AOA and AON, PERT and CPM – Previous Year Questions
14 GATE previous year questions on Project planning and scheduling: AOA and AON, PERT and CPM (Construction Management, Civil Engineering) with answers and explanations, from every paper.
14 questions worth 26 marks in all (2 1-mark, 12 2-mark). Asked between 2016 and 2025, so you can see how the topic has been tested over time.
- GATE 2017 CE (CE1) Q55 – A project has activities with predecessors and durations in days: P (none, 6); Q (P, 15); R (Q and T, 12); S (R, 16); T (P, 10); U (Q and T, 14); V…
- GATE 2016 CE (CE2) Q20 – A construction project has twelve activities. Durations (days): A inauguration 1; B foundation work 7; C structural construction-1 30; D structural…
- GATE 2016 CE (CE2) Q49 – The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are…
- GATE 2016 CE (CE1) Q49 – The four activities on a PERT critical path have optimistic, most likely and pessimistic durations (days) of (8,10,14), (6,8,11), (5,7,10) and…
- GATE 2017 CE (CE2) Q28 – Project completion time is normally distributed with mean 200 days and standard deviation 6.1 days. The maximum completion time for 95% probability is…
- GATE 2019 CE (CE1) Q47 – The construction project network is shown. Data below give normal duration / crash duration (days), normal cost / crash cost (INR): P: 6 / 4, 15000 /…
- GATE 2021 CE (CE2) Q52 – Project activities (duration days, predecessors): A(6,none), B(10,A), C(14,A), D(8,B), E(12,C), F(8,C), G(16,D and E), H(8,F and G), K(2,B), L(5,G and…
- GATE 2021 CE (CE1) Q53 – A project has activities N(2,none), P(5,N), Q(3,N), R(4,P), S(5,Q), T(8,R), U(7,R and S), V(2,U), W(3,U), X(5,T and V), Y(1,W), Z(3,X and Y), with…
- GATE 2022 CE (CE2) Q53 – Activities: A (10 days, none); B (12, none); C (5, after A); D (14, after B); E (10, after B and C). Find total float of E (integer days).
- GATE 2022 CE (CE1) Q39 – The activities are: Activity Duration (days) Depends on --- --- --- P 10 — Q 12 — R 5 P S 10 Q T 10 P, Q Which combination is correct?
- GATE 2024 CE (CE2) Q38 – A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12…
- GATE 2024 CE (CE2) Q52 – The table shows the activities and their durations and dependencies in a project. Activity Duration (Days) Depends on --- --- --- A 8 - B 4 A C 4 B D…
- GATE 2025 CE (CE2) Q53 – The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are…
- GATE 2025 CE (CE1) Q42 – In the context of construction project management, which of the following statements is/are true: