GATE 2025 CE (CE1) – Question 42
In the context of construction project management, which of the following statements is/are true:
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (B) The programme evaluation and review technique (PERT) is best suited for projects with large uncertainties in the duration of activities; (D) Free float is the amount of time by which the start of an activity can be delayed without causing a delay in the start of a following activity
Explanation
A dummy activity only shows a dependency, so it takes no time and no resources, and A is false. PERT uses three time estimates for each activity, so it suits projects where durations are very uncertain, and B is true. The critical path is found by CPM or PERT network analysis, not from a Gantt bar chart, so C is false. Free float is the delay an activity can take without delaying the early start of the activities that follow it, so D is true.