GATE 2022 CE (CE1) – Question 39
The activities are:
| Activity | Duration (days) | Depends on |
|---|---|---|
| P | 10 | — |
| Q | 12 | — |
| R | 5 | P |
| S | 10 | Q |
| T | 10 | P, Q |
Which combination is correct?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) Total duration of the project = 22 days, Critical path is Q → S
Explanation
The independent starts P and Q finish on days 10 and 12. R finishes on day 15; S on day 22; T cannot start until both P and Q finish, so it also finishes on day 22.
The project duration is **22 days**, with critical routes **Q–S** and **Q–T**. Option **A** gives a correct critical path and duration.