GATE 2024 CE (CE2) – Question 52

Construction Management · Project planning and scheduling: AOA and AON, PERT and CPM · 2 marks · Numerical answer

The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is ___________ (in integer).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 30

Explanation

Work out the earliest finish of each activity. A: 8. B: 12. C: 16. F: 12. G: 16. K: 18. L starts after F (12) and K (18), so it starts at 18 and finishes at 24. D starts after C (16) and L (24), so it finishes at $24 + 4 = 28$. H starts after G (16) and L (24), so it finishes at $24 + 6 = 30$. The project duration is the largest, 30 days.