GATE 2016 CE (CE2) – Question 49
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. The critical duration for this construction project is

Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (C) 15 days
Explanation
Forward-pass earliest event times are E20=2,E30=5,E40=6. Dummy links give E50=max(5,6)=6 and E60=max(2+3,6)=6. E70=max(5+5,6+3)=10; E80=max(10+3,6+2)=13; E90=15. Thus the critical project duration is **15days, C**.