In the Critical Path Method (CPM), the cost–time slope of an activity is ______.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (D) (Crash cost − Normal cost) / (Normal time − Crash time)
Explanation
Crashing adds cost while reducing duration. Cost per unit time saved is the incremental cost divided by normal duration minus crash duration. Both increments are positive under usual assumptions. **Answer: D.**