GATE 2016 ME (ME3) – Question 35
In PERT chart, the activity time distribution is
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (D) Beta
Explanation
Classical PERT models uncertain activity duration by a beta distribution, allowing asymmetry within optimistic and pessimistic bounds. Thus **D**. Its three estimates give expected duration(a+4m+b)/6; normal approximations, when used for a path total, do not change the activity-level assumption.