GATE 2021 ME (ME1) – Question 45

Operations Research · Network flow models, PERT and CPM · 2 marks · Numerical answer

Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.

ActivityABCD
Mean (days)611815
Variance (days²)4949

The probability that the project will be completed within 40 days is _____ (round off to two decimal places). (Note: Probability is a number between 0 and 1).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 0.49 to 0.51

Explanation

The sum is normal with mean 6+11+8+15=40 days and variance 4+9+4+9=26 days².

The requested deadline equals the mean. Normal symmetry gives $P(T\le40)=\Phi(0)=\mathbf{0.50}$.