GATE 2021 ME (ME2) – Question 18
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (B) 9
Explanation
Independent activity variances add. Each variance is 3²=9, so total path variance is 9×9=81.
Take the square root to obtain **standard deviation 9 (B)**. Adding standard deviations directly would incorrectly give 27.