GATE 2019 ME (ME1) – Question 65

Operations Research · Network flow models, PERT and CPM · 2 marks · Numerical answer

A project has activities with immediate predecessors and durations (weeks): P: none, 5; Q: none, 1; R: Q, 2; S: P and R, 4; T: P, 6; U: S and T, 3. All activities other than S take these durations. Find the maximum S duration (weeks) without delaying completion.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 6 to 6

Explanation

P finishes at week 5 and R at week 3, so S starts at week 5. T finishes at $5+6=11$; U finishes at week 14. S must finish by week 11, allowing duration $11-5=\mathbf{6}$ weeks.