A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is _____ hours (answer in integer).
The earliest finish times are A: 4, B: 12, C: 9, D: 14, E: 19, F: 15, G: 17 and H: 28. The project length is 28 hours. Going backwards, H must start at 19, so G must finish by 19 and start by 16, so D must finish by 16 and start by 14. D can start as early as 12, so its slack is $14 - 12 = 2$ hours.
More Network flow models, PERT and CPM questions
GATE 2022 ME (ME2) Q59– A project consists of five activities (A, B, C, D and E). The duration of each activity…
GATE 2021 ME (ME1) Q45– Activities A, B, C and D form the critical path for a project with a PERT network. The…
GATE 2021 ME (ME2) Q18– A PERT network has 9 activities on its critical path. The standard deviation of each…
GATE 2020 ME (ME1) Q23– In the Critical Path Method (CPM), the cost–time slope of an activity is .
GATE 2020 ME (ME2) Q33– The activity-on-node network labels activities A–L and shows their durations in hours…
GATE 2019 ME (ME1) Q65– A project has activities with immediate predecessors and durations (weeks): P: none, 5; Q:…