GATE 2025 ME – Question 65

Operations Research · Network flow models, PERT and CPM · 2 marks · Numerical answer

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is _____ hours (answer in integer).

ActivityImmediate predecessorDuration (hours)
A-4
BA8
CA5
DB2
EB7
FC6
GD3
HE, F, G9

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 2

Explanation

The earliest finish times are A: 4, B: 12, C: 9, D: 14, E: 19, F: 15, G: 17 and H: 28. The project length is 28 hours. Going backwards, H must start at 19, so G must finish by 19 and start by 16, so D must finish by 16 and start by 14. D can start as early as 12, so its slack is $14 - 12 = 2$ hours.