The GATE Grind

GATE 2022 ME (ME2) – Question 59

Operations Research · Network flow models, PERT and CPM · 2 marks · Numerical answer

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).

ActivityOptimisticMost likelyPessimisticPredecessors
A456None
B135A
C123A
D246C
E345B, D

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 15

Explanation

**Step 1: PERT expected durations**, $t_e=\dfrac{a+4m+b}6$.

Activity$t_e$
A$(4+20+6)/6=5$
B$(1+12+5)/6=3$
C$(1+8+3)/6=2$
D$(2+16+6)/6=4$
E$(3+16+5)/6=4$

**Step 2: network.** A first; then B and C in parallel (both after A); D follows C; E follows both B and D.

**Step 3: paths.**
- A → B → E: $5+3+4=12$ weeks
- A → C → D → E: $5+2+4+4=15$ weeks

**Step 4: project time** is the longest path, the critical path A–C–D–E:
$$T_E=\mathbf{15\text{ weeks}}.$$