GATE 2026 ME – Question 65

Operations Research · Network flow models, PERT and CPM · 2 marks · Numerical answer

The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic ($t_o$), most likely ($t_m$), and pessimistic ($t_p$) are given in the table below.

Activity$t_o$$t_m$$t_p$
1-22412
1-3246
1-43411
2-5369
3-42514
3-5333
4-53615
5-6258

The expected project length is ________ weeks (*in integer*).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 22

Explanation

The expected time of each activity is $\frac{t_o + 4t_m + t_p}{6}$. This gives 1-2: 5, 1-3: 4, 1-4: 5, 2-5: 6, 3-4: 6, 3-5: 3, 4-5: 7 and 5-6: 5. The paths to the end are 1-2-5-6 with $5 + 6 + 5 = 16$, 1-3-5-6 with 12, 1-4-5-6 with 17, and 1-3-4-5-6 with $4 + 6 + 7 + 5 = 22$. The longest path sets the project length, which is 22 weeks.