The GATE Grind

GATE 2025 PI – Question 54

Manufacturing Processes I · Casting · 2 marks · Numerical answer

Casting solidification starts at 10:00 am. Centerline metal starts solidifying at 10:03 and finishes at 10:10. Casting is completely solid when the centerline finishes. Find centerline feeding resistance CFR (% integer).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 70 to 70

Explanation

Centerline freezing duration is 10 − 3 = 7 minutes, while total casting solidification time is 10 minutes. Therefore $\mathrm{CFR}=100(7/10)=\mathbf{70\%}$.

More Casting questions

All Casting questions →