GATE Power Systems: Economic Load Dispatch (with and without considering transmission losses) – Previous Year Questions

9 GATE previous year questions on Economic Load Dispatch (with and without considering transmission losses) (Power Systems, Electrical Engineering) with answers and explanations, from every paper.

9 questions worth 15 marks in all (3 1-mark, 6 2-mark). Asked between 2014 and 2026, so you can see how the topic has been tested over time.

  1. GATE 2015 EE (EE2) Q50 (2 marks, Numerical answer) – Incremental costs in Rs/MWh are dC1/dP1=0.2P1+50 and dC2/dP2=0.24P2+40, with 20≤P1,P2≤150 MW. At the initial dispatch they are 76 and 68.8. Redispatch…
  2. GATE 2014 EE (EE1) Q52 (2 marks, Multiple choice) – Two plants have fuel costs C 1=0.05P g12+AP g1+B and C 2=0.10P g22+3AP g2+2B, with constants A,B. They optimally share 1000 MW at incremental cost…
  3. GATE 2015 EE Q51 (2 marks, Numerical answer) – Consider the economic dispatch problem for a power plant having two generating units. The fuel costs in Rs/MWh along with the generation limits for…
  4. GATE 2021 EE Q20 (1 mark, Multiple choice) – Two generators have cost functions F 1 and F 2. Their incremental-cost characteristics are dF 1dP 1=40+0.2P 1 dF 2dP 2=32+0.4P 2 They need to deliver…
  5. GATE 2022 EE Q43 (2 marks, Multiple choice) – The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by Plant 1: C 1=350+6P 1+0.004P 12 Plant 2: C 2=450+aP 2+0.003P…
  6. GATE 2023 EE Q21 (1 mark, Multiple choice) – The expressions of fuel cost of two thermal generating units as a function of the respective power generation P G1 and P G2 are given as F 1(P…
  7. GATE 2024 EE Q34 (1 mark, Numerical answer) – The incremental cost curves of two generators (Gen A and Gen B) in a plant supplying a common load are shown in the figure. If the incremental cost of…
  8. GATE 2025 EE Q64 (2 marks, Numerical answer) – Two units, rated at 100 MW and 150 MW, are enabled for economic load dispatch. When the overall incremental cost is 10,000 Rs./MWh, the units are…
  9. GATE 2026 EE Q58 (2 marks, Numerical answer) – A system with two generators G1 and G2 (without generator limits) is shown. The total load on the system is 1184 MW. The expressions for the cost of…