GATE 2016 EC (EC2) – Question 5

General Aptitude · Quantitative Aptitude: Data Interpretation, Arithmetic and Number Computation · 1 mark · Multiple choice

S, M, E and F work shifts on a project. M works at twice the efficiency of the others but for half as many days as E. S and M have 6-hour daily shifts; E and F have 12-hour shifts. The ratio of M’s contribution to E’s is

  1. 1:1
  2. 1:2
  3. 1:4
  4. 2:1

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 1:2

Explanation

Work equals hourly efficiency multiplied by hours per day and days. Let E's efficiency be r and E's days be d. Then E contributes 12rd.

M has efficiency 2r, daily hours 6 and days d/2, contributing $2r\cdot6\cdot d/2=6rd$. Hence M:E=6:12=**1:2, B**.