Causal forecasting links the forecast variable to explanatory variables. Regression explicitly models that relationship, D. The naive, moving-average and basic exponential-smoothing methods forecast from the series’ own past behaviour rather than an external causal predictor.
More Production Control questions
GATE 2020 PI Q35– The product structure shows quantities needed per parent. How many units of component D…
GATE 2020 PI Q63– A factory produces200 components/day for300 days/year. Demand is15000/year, setup…
GATE 2026 PI Q23– Which is NOT an assumption of the economic order quantity (EOQ) model?
GATE 2026 PI Q35– A toy-car plant has monthly demands: September 8000; October 6500; November 10500;…
GATE 2026 PI Q59– A central server processes one program at a time. Four programs are ready at 10:00 am.…
GATE 2025 PI Q33– Annual demand is 2000 bulbs, ordering cost ₹300/order and annual holding cost ₹30/bulb.…