The basic EOQ model balances ordering and holding costs with known steady demand and replenishment without shortages. It does not allow stockouts, so **C** is the intended answer. Zero lead time is a common simplification; the model also admits known constant positive lead time through a reorder point.
More Production Control questions
GATE 2026 PI Q35– A toy-car plant has monthly demands: September 8000; October 6500; November 10500;…
GATE 2026 PI Q59– A central server processes one program at a time. Four programs are ready at 10:00 am.…
GATE 2025 PI Q33– Annual demand is 2000 bulbs, ordering cost ₹300/order and annual holding cost ₹30/bulb.…
GATE 2025 PI Q60– Annual demand is 5000 units, ordering cost ₹400/order and annual holding rate 30% of unit…
GATE 2024 PI Q25– Which forecasting method needs the least historical data?
GATE 2024 PI Q30– Which ONE OR MORE are supply-chain decision areas?