Correct answer: (D) Painting cannot start late without delaying project completion.
Explanation
Zero total float means any delay beyond the scheduled start delays project completion, assuming the other activities keep their planned durations. Its six-day duration excludes a dummy activity. Therefore **D**.
More Project Management questions
GATE 2025 PI Q41– The project network shows activities A–H and durations in days. Find its critical path.
GATE 2024 PI Q41– Activities A,B,C have no predecessors; D follows A,B; E follows B,C; F follows A,B. Find…
GATE 2023 PI Q53– Project activities A–J have durations (days) A:8, B:10, C:8, D:7, E:16, F:15, G:18, H:14,…
GATE 2022 PI Q35– Activities A–G have expected durations 4,5,4,1,7,6,8 minutes and variances 1,1,1,0,4,1,4…
GATE 2021 PI Q52– Activities and (duration in days; predecessors) are A:(2;–), B:(3;–), C:(2;A), D:(4;A,B),…