Project activities have the following duration in weeks and immediate predecessors.

P: 7, none; Q: 4, none; R: 2, Q; S: 11, P; T: 9, P and R; U: 9, Q; V: 4, T and U.

Find the CPM project completion time in weeks.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 20 to 20

Explanation

Earliest finishes are P7,Q4,R6,S18. T starts after both P and R at7, finishing16; U finishes13. V starts at max(16,13)=16 and finishes20. The project also requires S, finished18, so total duration is20 weeks. Critical path P–T–V gives7+9+4.