GATE 2020 PI – Question 60
Project activities have the following duration in weeks and immediate predecessors.
P: 7, none; Q: 4, none; R: 2, Q; S: 11, P; T: 9, P and R; U: 9, Q; V: 4, T and U.
Find the CPM project completion time in weeks.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 20 to 20
Explanation
Earliest finishes are P7,Q4,R6,S18. T starts after both P and R at7, finishing16; U finishes13. V starts at max(16,13)=16 and finishes20. The project also requires S, finished18, so total duration is20 weeks. Critical path P–T–V gives7+9+4.