GATE 2025 PI – Question 41

Operations Research and Operations Management · Project Management · 2 marks · Multiple choice

The project network shows activities A–H and durations in days. Find its critical path.

Diagram for GATE 2025 PI question 41
  1. 1–2–3–6
  2. 1–4–3–6
  3. 1–5–6
  4. 1–4–5–6

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 1–4–3–6

Explanation

Sum durations along each route: 1–2–3–6 takes 3+5+6 = 14 days; 1–4–3–6 takes 2+7+6 = 15; 1–5–6 takes 4+2 = 6; 1–4–5–6 takes 2+1+2 = 5. The longest route determines project duration, so **1–4–3–6, B**.