GATE 2024 PI – Question 41

Operations Research and Operations Management · Project Management · 2 marks · Multiple choice

Activities A,B,C have no predecessors; D follows A,B; E follows B,C; F follows A,B. Find the minimum dummy activities for an activity-on-arrow network.

  1. 0
  2. 1
  3. 2
  4. 3

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (D) 3

Explanation

A and B must merge before D,F, while B and C must merge before E. Let A end at event U, B at V and C at W. Add dummy V→U and dummy V→W to enforce the two distinct predecessor combinations. From U, draw D to the finish and F to a separate event, then a third dummy from that event to the finish; this avoids duplicate arrows with identical endpoints for D and F. E runs W→finish. Thus **three dummies, D**, are sufficient and needed under the standard unique-arrow AOA convention.