GATE Operations Research and Operations Management: Project Management – Previous Year Questions
6 GATE previous year questions on Project Management (Operations Research and Operations Management, Production and Industrial Engineering) with answers and explanations, from every paper.
- GATE 2021 PI Q52 – Activities and (duration in days; predecessors) are A:(2;–), B:(3;–), C:(2;A), D:(4;A,B), E:(4;C), F:(3;C), G:(X;D,E), H:(2;F,G). Project duration is…
- GATE 2022 PI Q35 – Activities A–G have expected durations 4,5,4,1,7,6,8 minutes and variances 1,1,1,0,4,1,4 respectively. The critical path is B,E,G. Find…
- GATE 2023 PI Q53 – Project activities A–J have durations (days) A:8, B:10, C:8, D:7, E:16, F:15, G:18, H:14, I:9, J:4. Predecessors are A:–, B:–, C:–, D:A, E:A, F:B,D,…
- GATE 2024 PI Q41 – Activities A,B,C have no predecessors; D follows A,B; E follows B,C; F follows A,B. Find the minimum dummy activities for an activity-on-arrow…
- GATE 2025 PI Q41 – The project network shows activities A–H and durations in days. Find its critical path.
- GATE 2026 PI Q24 – Painting takes six days in a construction project, with total float = free float = 0. Which statement is true?