GATE 2019 PI – Question 63

Operations Research and Operations Management · Project Management · 2 marks · Numerical answer

A PERT project network consists of 5 activities A to E. Activity predecessor-successor (P-S) relationships and time estimates (optimistic, most likely, pessimistic, in days) are: A: 1-2, 2, 4, 6; B: 2-3, 4, 5, 12; C: 2-4, 5, 8, 11; D: 3-5, 2, 5, 08; E: 4-5, 4, 6, 14. The variance (in days) of the critical path is (round off to 2 decimal places)

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 4.00 to 4.40

Explanation

We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort