Mining Geology, Mine Development and Surveying · Mine Development · 1 mark · Multiple choice
The drivage diagram assigns2.0,3.0 and1.0 kg per hole to Sections1,2 and3 respectively. Consecutive sections have25 ms delay. What is the maximum charge per delay in kg?
Count the holes in each simultaneously initiated section: four in Section1, four in Section2 and eight in Section3. Their separate charges are4×2=8 kg,4×3=12 kg and8×1=8 kg. The largest single-delay total is12 kg, B; distinct delay groups are not added together.
More Mine Development questions
GATE 2026 MN Q41– Match sinking methods P piling,Q caisson,R cementation,S freezing to applications:1…
GATE 2026 MN Q58– Each hole in the displayed bench-blast pattern contains49 kg explosive. Hole labels give…
GATE 2025 MN Q27– An explosive’s detonation velocity is10500 m/s. In the shown D’Autriche test the fuse…
GATE 2025 MN Q46– A surface-mine blast has burden3.5 m,spacing4.5 m,bench height10 m,subgrade drilling1…
GATE 2024 MN Q27– An explosive has density 1.2 g/cm³ and heat 900 cal/g. ANFO has density 0.8 g/cm³ and heat…
GATE 2024 MN Q34– A VCR stope uses 165 mm diameter holes. Under the spherical-charge approximation of length…