GATE 2026 MN – Question 61

Mining Methods and Machinery · Mining Methods · 2 marks · Numerical answer

A bord-and-pillar panel has24 pillars of40×40 m centre-to-centre spacing,4 m galleries and3 m extraction height. Coal specific gravity is1.4 and depillaring recovers80%. Incubation is6 months of25 working days each. Find minimum production in tonne/day to one decimal.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 696.0 to 697.0

Explanation

The remaining pillar side is40−4=36 m. Recoverable pillar coal is24×36²×3×1.4×0.8=104509.44 tonnes. Available time is6×25=150 working days. Required average production is104509.44/150=696.7296 tonne/day, or696.7. The gallery coal has already been removed during development.