GATE 2021 AR – Question 62
Activities P, Q, R, S, T have durations 2, 4, 5, 6, 3 weeks. P’s successor is R; Q’s successors are R and S; R’s successor is T; S and T have none. Find total project duration in weeks, as an integer.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 12 to 12
Explanation
P finishes at 2 and Q at 4. R waits for both and finishes at 4+5=9; T then finishes at 12. S follows Q and finishes at 4+6=10. The longest completion is 12 weeks on Q–R–T, so the project duration is 12.
More Construction project management techniques e.g. PERT, CPM questions
- GATE 2026 AR — Architecture Q46
- GATE 2026 AR — Planning Q46
- GATE 2025 AR — Architecture Q46
- GATE 2025 AR — Planning Q46
- GATE 2024 AR — Architecture Q45
- GATE 2024 AR — Planning Q45
All Construction project management techniques e.g. PERT, CPM questions →