GATE 2019 PI – Question 48

Operations Research and Operations Management · Production Control · 2 marks · Multiple choice

The man-hours required ($T_n$) to manufacture the $n^{\mathrm{th}}$ unit in a plant is given by $T_n=T_1n^b$, where $b=-0.322$ at the 80% learning rate. If the manufacturing time for the first unit ($T_1$) is 80 man-hours, the total time (in man-hours) required to manufacture the first 4 units, at 80% learning rate, is

  1. 322.11
  2. 251.35
  3. 103.76
  4. 51.19

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 251.35

Explanation