GATE 2022 CE (CE1) – Question 24

Geomatics Engineering · Distance and angle measurement, levelling, traversing, triangulation, total station · 1 mark · Multiple choice

A line between stations P and Q laid on a slope of 1 in 5 was measured as 350 m using a 50 m tape. The tape is known to be short by 0.1 m. The corrected horizontal length (in m) of the line PQ will be

  1. 342.52
  2. 349.30
  3. 356.20
  4. 350.70

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (A) 342.52

Explanation

The short tape makes the true slope distance smaller: $L_s=350(49.9/50)=349.3$ m. A slope of 1 in 5 gives $\tan\theta=1/5$.

Thus $L_h=L_s/\sqrt{1+(1/5)^2}=342.5168$ m. **Answer: 342.52 m (A)**. Both tape correction and slope reduction decrease the length.