GATE 2025 PI – Question 48

Industrial Engineering · Work System Design · 2 marks · Numerical answer

A worker receives 30 minutes personal allowance during an eight-hour shift. Normal product time is five minutes. Find standard time (integer seconds).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 315 to 325

Explanation

Available work time is 480 − 30 = 450 minutes. Allowance is specified as a fraction of total shift, so standard time is $5(480/450)=16/3$ minutes = **320 seconds**.