Industrial Engineering · Work System Design · 1 mark · Numerical answer

Standard time per machine job is 10 min. Five machines are each available 300 hours/month with average utilization 80%. Find maximum monthly production (integer jobs).

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 7200 to 7200

Explanation

Effective time = 5 × 300 × 60 × 0.80 = 72000 machine-minutes/month. Divide by 10 minutes/job to obtain **7200 jobs/month**.