An outline chart records main operations and inspections across the product sequence. String diagrams trace movement on a layout. Multiple activity charts coordinate gang activities on a time scale. Two-handed charts compare left/right hand motions during manual assembly. **P–3,Q–1,R–2,S–4, B**.