GATE 2010 CS (CS1) – Question 9
Five skilled workers complete a job in 20 days, eight semiskilled workers in 25 days, and ten unskilled workers in 30 days. How long will two skilled, six semiskilled and five unskilled workers working together take?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (D) 15 days
Explanation
The daily rates of one worker are 1/100, 1/200 and 1/300 of the job respectively. The combined rate is 2/100+6/200+5/300=(6+9+5)/300=1/15. Therefore the team takes fifteen days, D, assuming constant additive productivity.