The timeline has 3 idle hours (0–1, 8–9 and 16–17), 2 breakdown hours (6–7 and 19–20), and 1 maintenance hour (23–24). Working time is therefore 24−3−2−1 = 18 hours. Available time excludes breakdown and maintenance: 24−2−1 = 21 hours. Utilisation is working time divided by available time, 18/21 × 100 = 85.71%.