Out of the following options, the most relevant information needed to specify the real power (P) at the PV buses in a load flow analysis is
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) solution of economic load dispatch
Explanation
At a PV bus the real power is scheduled, and the schedule comes from the economic load dispatch solution, which decides how much each generator should produce.