Mining Methods and Machinery · Mining Methods · 2 marks · Numerical answer
An underground copper mine sends 2500 tonnes of ore per day to the concentrator plant, having an average grade of 1.2% Cu. The plant produces concentrate of 25.0% Cu with a recovery of 93.0%. The solids portion of tailings generated from the plant per day, in tonnes, is (round off to 1 decimal place).
We are sorry we couldn't write detailed soluition for this, we are working on it!, please consider asking your own AI, its just 2-3 clicks with very minimum effort
More Mining Methods questions
GATE 2020 MN Q57– For a development heading, the blasting parameters are: cross-section 6.0 m × 5.0 m; total…
GATE 2020 MN Q64– A vertical stoping block of length 60.0 m, height 40.0 m and average width 1.5 m has sharp…
GATE 2026 MN Q25– A20 m thick orebody dips75°. Both ore and host rock are strong, and production drilling…
GATE 2026 MN Q57– A dragline bucket holds20 m³ with fill factor0.9. Digging/filling takes20 s, total…
GATE 2026 MN Q59– The cut-and-fill stope dimensions are shown. Pillars are4×4 m, separated by clear13 m…
GATE 2026 MN Q61– A bord-and-pillar panel has24 pillars of40×40 m centre-to-centre spacing,4 m galleries…