GATE 2026 ME – Question 47
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
| Job | Due date | Work remaining (in days) |
|---|---|---|
| M | 26 | 5 |
| N | 24 | 10 |
| O | 28 | 10 |
| P | 31 | 5 |
Which job(s) has/have critical ratio less than unity?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (A) Job N and Job O
Explanation
The critical ratio is the time left until the due date divided by the work remaining. On day 20: M gives $\frac{26 - 20}{5} = 1.2$, N gives $\frac{24 - 20}{10} = 0.4$, O gives $\frac{28 - 20}{10} = 0.8$ and P gives $\frac{31 - 20}{5} = 2.2$. Jobs N and O have a ratio below 1.