GATE 2022 ME (ME2) – Question 41

Production Planning and Control · Aggregate production planning, scheduling and material requirement planning · 2 marks · Multiple choice

Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is ______ hours.

PartMilling (hours)Polishing (hours)
P186
P232
P334
P446
P557
P664
P721
  1. 31
  2. 33
  3. 30
  4. 32

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 33

Explanation

This is a two-machine flow shop (milling, then polishing), so **Johnson's rule** gives the order with the shortest total completion time.

**Step 1: split the parts.**
- Parts with milling time ≤ polishing time: P3 (3, 4), P4 (4, 6), P5 (5, 7). Put them **first**, in increasing order of milling time: P3, P4, P5.
- The other parts: P1 (8, 6), P2 (3, 2), P6 (6, 4), P7 (2, 1). Put them **last**, in decreasing order of polishing time: P1 (6), P6 (4), P2 (2), P7 (1).

**Step 2: sequence.** P3 – P4 – P5 – P1 – P6 – P2 – P7.

**Step 3: timetable** (a part is polished when milling of it is done and the polisher is free).

PartMilling endsPolishing startsPolishing ends
P3337
P47713
P5121320
P1202026
P6262630
P2293032
P7313233

The last polishing ends at **33 hours**, which is the minimum (milling alone takes 31 hours and P7 still needs 1 hour of polishing, and Johnson's rule is optimal).