GATE 2017 ME (ME1) – Question 62
Four jobs P, Q, R, S are available together for one machine. Their processing times are 15, 9, 22 and 12 days respectively. Find the shortest possible average flow time in days.
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: 31 to 31
Explanation
When all jobs are available at time zero, shortest-processing-time order minimizes the sum of completion times. The order is Q, S, P, R, with completion times $9,9+12=21,21+15=36,36+22=58$ days. Average flow time is $(9+21+36+58)/4=124/4=31$ days.