GATE 2022 ME (ME1) – Question 42

Production Planning and Control · Aggregate production planning, scheduling and material requirement planning · 2 marks · Multiple choice

Activities A to K are required to complete a project. The time estimates and the immediate predecessors of these activities are given in the table. If the project is to be completed in the minimum possible time, the latest finish time for the activity G is ____________ hours.

ActivityTime (hours)Immediate predecessors
A2−
B3−
C2−
D4A
E5B
F4B
G3C
H10D, E
I5F
J8G
K3H, I, J
  1. 5
  2. 10
  3. 8
  4. 9

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 10

Explanation

The earliest finish times are: D = 6, E = 8, F = 7, H = $8 + 10 = 18$, I = 12, G = 2, J = 10, and K starts at $\max(18, 12, 10) = 18$ and finishes at 21. So the project time is 21 h. Going backwards, K must start at 18, so J must finish by 18 and start by $18 - 8 = 10$. G precedes only J, so its latest finish time is 10 h.