GATE 2020 ME (ME2) – Question 23
In Materials Requirement Planning, inventory holding cost is very high and setup cost is zero. Which lot-sizing approach should be used?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: (B) Lot-for-Lot
Explanation
With no setup penalty there is no saving from combining periods. High holding cost makes early production expensive. Lot-for-lot supplies exactly each period’s net requirement and avoids unnecessary carryover. **Answer:B**.