GATE 2018 ME (ME2) – Question 8
A contract must be completed in 52 days. There are 125 identical robots, each operating 7 hours/day. After 39 days, five-sevenths of the work is complete. How many additional robots are required to finish on time if each now operates 8 hours/day?
Practise this question in The GATE Grind →
Show answer and explanation
Correct answer: MTA
Explanation
The official key awards **marks to all**. Completed work requires $125(7)(39)=34125$ robot-hours and equals five-sevenths of the total. Remaining work is $34125(2/5)=13650$ robot-hours. Remaining time is 13 days of 8 h/day, requiring $13650/(13\times8)=131.25$ robot equivalents. Thus 132 whole robots, or **7 additional robots**, are needed. None of the choices fits.