The GATE Grind

GATE 2026 MN – Question 47

Mineral Economics, Mine Planning, Systems Engineering · Systems Engineering · 2 marks · Numerical answer

Assign four jobs J1–J4 to engineers S1–S4, one job each. Costs by row are S1:(50,50,unavailable,20); S2:(70,40,20,70); S3:(90,30,50,unavailable); S4:(70,20,60,30). Find minimum total cost as an integer.

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 130 to 130

Explanation

Enumerate feasible one-to-one assignments, excluding S1–J3 and S3–J4. One optimum is S1–J4 at20,S2–J3 at20,S3–J2 at30 and S4–J1 at70, totalling140; a better assignment is S1–J1 at50,S2–J3 at20,S3–J2 at30,S4–J4 at30, totalling130. Exhaustive assignment comparison confirms130 is minimal.

More Systems Engineering questions

All Systems Engineering questions →