Mineral Economics, Mine Planning, Systems Engineering · Systems Engineering · 1 mark · Multiple choice

The project network is shown. Activities A, B, C, D, E have durations 5, 6, 8, 3, 4 weeks and crash costs 4, 2.5, 2, 3, 4 lakh rupees/week respectively. Find the least cost to shorten the project by one week.

Diagram for GATE 2024 MN question 20
  1. 2.0
  2. 2.5
  3. 3.0
  4. 4.0

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) 2.5

Explanation

The A–B–D–E path takes 5+6+3+4=18 weeks, while A–C–E takes 17. On the critical path B has the lowest one-week crash cost, 2.5 lakh. Crashing B makes both paths 17 weeks and shortens the project by one week. Thus B; cheaper activity C is initially noncritical.