GATE 2026 MN – Question 31

Mineral Economics, Mine Planning, Systems Engineering · Systems Engineering · 1 mark · Numerical answer

Activities in the project network are labelled(expected days,standard deviation in days). Find the standard deviation of project completion time to one decimal.

Diagram for GATE 2026 MN question 31

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: 3.0 to 3.0

Explanation

Path A–C–D–F takes12+15+18+6=51 days; B–E takes23+27=50 days. The first path is the expected-time critical path. Under the usual independent-activity PERT approximation its variance is0²+1²+2²+2²=9 days², so standard deviation3.0 days. This approximation follows the critical path, not the sum of every activity variance.